Revitalisation of Goodhew Park Taralga

PROJECT UPDATE

  • Work commenced in March and will be completed in June 2019
  • Drainage improvements have been completed
  • Playground equipment has been installed and is ready for use
  • The old toilet block has been demolished and a cement pad is in place
  • Toilet block is completed and ready for use June 2019
  • Shelter, picnic benches and BBQ are available for use June 2019
  • An outdoor tap for cleaning purposes and turfing (due to winter mud) has been installed - July 2019
  • This project has been completed and is ready for school holidays - July 2019

SCOPE

  • Supply, installation of new toilet block
  • Establishing sewer, water and electric connection
  • Demolition of existing toilet facilities
  • Playground repair and equipment installation
  • Development and improvement of drainage facilities

DRAWINGS AND IMAGES

SCHEDULE

BUDGET

  • Budget (available) $210,000 (NSW Govt Grant/ULSC)
  • Budget (estimated) $242,000 (NSW Govt Grant/ ULSC and extra $32,000 funding towards Shelters and BBQ from Council)