Re-Energising the Collector Community Project

PROJECT UPDATE

  • A revised version of the design was completed in May 2019
  • Tendering will take place in June 2019
  • Approval of the tenderer will be sought at the July 2019 Council meeting
  • Work is expected to take place from August 2019

SCOPE

  • Design and construction of a shared pathway (and raised boardwalk) along the south side of Bourke Street from the Oval to Collector Rural Fire Shed with the provision for the extension of the pathway along Bourke Street towards the memorial Hall should the budget allow, signage and line marking as required
  • Design and construction of a pathway along Lorn Street from Goulburn Street to Bourke Street in line with PAMP, signage and line marking as required
  • Installation of 2 sheltered picnic tables on cement pads near the outdoor gym at Collector Oval
  • DESIGN

SCHEDULE

  • 30-06-2018 to 20-01-2020 (as per funding deed)
  • A revised work schedule will be advised in May 2019

BUDGET

  • Budget (available) $220,000
  • Budget (estimated) $220,000