Pedestrian Access and Mobility Plan SCCF1

PROJECT UPDATE

  • Pathway on Church Street Taralga completed
  • Laggan Pathway design in line with community feedback completed
  • Work on Laggan Pathway is expected to take place in September 2019
  • Variation for Gunning pathways has been approved - July 2019
  • Work on Gunning footpath on Hume Street is underway - August 2019
  • Work on Laggan pathway is expected to start in September 2019

SCOPE

SCHEDULE

  • 30-06-2018 to 20-01-2020 (as per funding deed)

BUDGET

  • Budget (available) $344,487
  • Budget (estimated) $344,487