Pat Cullen Reserve Community Recreation Area, Kiamma Creek

PROJECT UPDATE

  • Footbridge is in place and completed
  • Pathway is expected to be completed by the end of October 2019 (there is a delay in finishing the pathway at Saleyards Road due to the boggy nature of the area. Work will be undertaked when the ground has been well drained)
  • Solar lights on the Laggan Road end of the pathway have been installed with the rest of the solar lighting being installed when the pathway has been completed.

SCOPE

  • Improvement of current gravel walkway by excavating, widening and concreting from Laggan Road to Spring Street Boardwalk
  • Walkway will be furnished with solar lighting for evening use
  • A foot bridge will be designed and constructed to complete the walkway in line with disability access requirements

DRAWINGS

  • Plans Footpath and Footbridge

SCHEDULE

BUDGET

  • Budget (available) $263,564
  • Budget (estimated) $263,564

MAP