Crookwell Memorial Oval Sports Centre

PROJECT UPDATE

  • Council has hired 2 portable ablution blocks – 6.0m * 3.0m each (with showers, basins, and toilets) and 2 change rooms – 6.0m * 3.0m each (with air conditioner) for the sports season in between 29 March – 18 July 2019. They have been installed on the Marsden Street side of the Oval.
  • Tilt up walls were completed April 2019
  • The veranda work has started in May 2019

FINAL DRAWINGS

SCOPE

  • Design and construction of new Community Sports Centre Building including gym, club room, canteen, toilets with disabled facilities, change rooms, refree room and storage
  • Demolition of existing toilets/gym and canteen blocks

SCHEDULE

BUDGET

  • Revised Budget (available) $1,651,000
  • Revised Budget (estimated) $1,651,000