Crookwell Landfill Upgrade (New Waste Cell)

Project Update

  • EPA approval of the new waste cell design obtained.
  • The remediation stage of the project, currently underway, requires substantial progress to provide access for the new cell construction.
  • Specification and Tender document under development, with construction to be supported by specialist landfill lining services.
  • Further approvals processes being progressed.

Scope

  • Construction of a new  landfill cell in accordance with the requirements of the NSW EPA Solid Waste Landfill Guidelines and EPA approved construction plans.

Design Documents

Schedule

  • Completion prior to 31 December 2019 in accordance with EPA Licencing requirements.

Budget

  • $1.78M