Collector Village Drainage Upgrade

PROJECT UPDATE

  • A Project Control Group has been formed to oversee the project and includes Trainee Engineers and Director of Works and Operations.
  • Council is consulting with Roads and Maritime Services and other stakeholders to clearly define the scope.
  • Project Schedule is being developed.

SCOPE

  • Needs - Improve drainage in the village of Collector and meet community expectation within the available funds;
  • Requirements - Engineering staff are developing technical specification to meet these “Needs”.
  • Known constraints are the culvert across the Federal Highway, known budget of $240,000 and higher community expectation to address drainage concerns quickly (project schedule).

SCHEDULE

  • A revised schedule/project plan will be advised in September 2018 when investigation and design has progressed.
  • This will be revised regularly to advise the community on the progress.

BUDGET

  • Budget (available) $240,000.