PROJECT UPDATE

  • A Project Control Group has been formed to oversee the project.
  • Council has consulted with Roads and Maritime Services and other stakeholders in the area.
  • Site Investigation and preliminary planning has been complete.
  • Detailed designs, bill of quantities and estimates have been completed.
  • Quotations are being sought for the work.
  • Drainage works are expected to commence by August 2019.

SCOPE

  • Improve drainage in the village of Collector
  • 5 (five) areas of significant overland flow have been identified to undertake drainage work in order to mitigate stormwater issues.

SCHEDULE

BUDGET

  • Budget (available) $240,000