Clifton Park Community Connections and Pathway

PROJECT UPDATE

  • Site visits along with prospective architectural consultants were conducted 10 & 21 August 2018
  • Site survey was completed 30 August 2018
  • Crookwell Neighbourhood Centre completed design with Upper Lachlan Shire Council October 2018
  • Walkway completed November 2018
  • Arrival of BBQ and Shelter mid December 2018
  • Installation of BBQ Shelter completed in January 2019
  • Progress Report lodged with grant body February 2019
  • Electrical pole and metering installed in March 2019.
  • BBQ installed in April 2019.
  • Solar lighting will be installed in May 2019

 

  • SCOPE
  • Design and construction of a 2m wide recreational pathway around the perimeter of Clifton Park joining with the outdoor gymnasium, skate park, cricket nets, playground and proposed toilet block and disabled BBQ area
  • Installation of a sheltered, disabled BBQ with necessary power on a concrete pad
  • Design and installation of solar lighting

SCHEDULE

  • 30-06-2018 to 20-01-2020 (as per funding deed)
  • This project is expected to be completed by April 2019 well ahead of scheduled completion date.

BUDGET

  • Budget (available) $112,189
  • Budget (estimated) $112,189